Summary
The skatepark expansion is officially finished — the board approved the final two payments to 5th Pocket Skateparks, totaling about $97,800.
At a glance
- Total mentions
- 5
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 8, 2026.
Impact analysis
Final payments to the skatepark contractor totaled $97,809.00.
Skaters and families who use the expanded skatepark.
Mentions & discussions (5)
Board of Public Works - Oct 8, 2026
The skatepark expansion is officially finished — the board approved the final two payments to 5th Pocket Skateparks, totaling about $97,800.
Board of Public Works - Aug 26, 2026
A $14,500 change order covered extra concrete maintenance the contractor found while on site — cheaper to fix it now than call them back later.
Board of Public Works - Jul 22, 2026
The city is paying out $57,000 to 5th Pocket Skateparks as the first pay estimate on the Manitowoc Skatepark expansion — construction is moving along.
Parks & Recreation Committee - Jun 25, 2026
Phase 3 of the X-Sports skatepark upgrade is fully funded through a West Foundation grant, about $20,000 in private fundraising, and a $100,000 city match. Old ramps come down this weekend, with new construction starting around July 20 and done by end of August.
Common Council - Feb 16, 2026
Bids were awarded for the Manitowoc Skatepark Expansion ($198,350) and Red Arrow Beach access improvements ($1.08 million).
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Manitowoc
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.